Carson has applied for permitting for repower and has the below listed tentative schedule

·       Sale of existing plant and equipment- Immediate

o   GE 7LM6000-PC-NGWG18

o   EM Generator 45,765 kVA

o   Shin Nippon 10.5 MW Steam Turbine

o   Shinko Brushless AC Generator

·     RFP Demolition- To be tendered 1 October 2017

·     RFP Repower Turbine- To be tendered 1 October 2017

·     RFP Site Engineering- To be tendered 1 November 2017

·     RFP Turbine Controls- To be tendered 1 November 2017

·     RFP Turbine Emissions, CEMS and Filtering- To be tendered 1 November 2017

·     RFP Construction and Fabrication Repower- - To be tendered 1 December 2017

·     RFP Integrated Battery Solution- To be tendered 15 January 2017

·     RFP Construction and Fabrication Energy Storage- To be tendered 1 February 2017